Production

TEEYER
The Production Process of AAC Block and Panel
The first step is to grind flyash or sand through using a ball mill , and make the mixture into a form of slurry to store in tanks.
Cement and processed lime are conveyed to silos for storage respectively.
Meanwhile,the wire straightening and cutting machine uncoils straightens the steel wire and cuts it to the required lengths for longitudinal bars and cross bars.
The adjusted and cut steel bars are welded into meshes , by using the multi-point welding machine automatically, or into cages by the spot-welder corresponding to the desired panel size and strength.
After being dipped in the anti-corrosion liquid and dired in the drying oven , the coated reinforcement meshes or cages are assenmbled with frames and positioned by holding pins. Then , they will be lifted to the appointed position by the crane , preparing to be fixed into mould.
The prepared raw materials shall be weighted by electronic scale , and then conveyed into the pouring mixer for high-speed mixing.
All of the weighing processes are controlled by the PLC system automatically.
During scaling and mixing , the empty mould is conveyed onto the pouring ferry cart , preparing for pouring .
The mixed slurry of raw materials is poured into empty mould , through the up-down pouring device. The filled mould is transported from the pouring ferry cart to the appointed rail.
When the mould leaves the ferry cart, the bubble processing machine starts to vibirate, in order to remove big bubbles caused by pouring.
During block production, the mould is directly conveyed to the pre-curing room by friction wheels for curing under constant temperature .
For panel production , the mould shall be transported to the pre-curing room , after meshes or cages are plugged into it by the crane .

When the cake reaches the cutting-requried hardness after pre-curing ,the mould is conveyed onto pre-curing ferry cart ,by friction wheels directly if only producing blocks ,for panel production ,the assembled frame and holding pins shall be pulled out of the mould prior to cutting ,then the mould can be conveyed onto ferry cart by friction wheels .
Ferry cart transports mould to the locating position under tilting hoister which takes the located mould to cutting line .
The tilting hoister turns the mould over by 90 degrees ,and puts it onto the first cutting cart for de-molding .
Then , the empty mould will be assembled with a cleaned side plate and taken to returning line for oiling ,waiting for the next pouring .
The first cutting cart carries the green cake passing through the horizontal cutting machine ,for 6 surfaces cutting or sides grooving .
Then the green cake continuously moves to the vertical cutting machine .
The exchange device jacks up the cake as well as side plate for vertical cutting .
During vertical cutting process ,pneumatic cylinder tension device swings back and forth .
After the cutting process , the second cutting cart comes to carry this cake together with the side plate to the semi-finished product hoister which will take the green cake to the tilting table to remove the waste at the top and bottom
After waste removal , the cake will be conveyed by the semi-finished product hoister to the trolley for grouping .
The grouped trolley will then be conveyed by friction wheels to the grouping ferry cart ,which carries the trolley to certain rail for autoclave grouping .
After the completion of the whole grouping process , the whole line of trolleys will be pushed into the autoclave together by the drawing mechanism.
The autoclaving-finished products will then be pulled out of the autoclave by the drawing mechanism automatically .
Trolleys are then separated by the automatic hook releasing device and conveyed to the after-autoclave ferry cart one by one by the drawing mechanism and friction wheels .
Then ,the ferry cart carries the trolleys to the returning line .
The finished-product loading hoister will take the mature cake onto the traverse device which conveys it to the lifting platform under the separator.
The mature cake is then separated by the separating frame device when the lifting platform elevates it .
After being separated ,the mature cake will be conveyed to the finished-product clamping hoister by side plate rollers .
Blocks and panels are then classified and taken to the packing line by the finished product hoister for stacking and strapping .
After packaging ,the finished products will be taken to the storage yard by forklifts or transported to the construction site directly .
The processes of this production line shall be repeated continuously according to the above process flow .

Contact Us

Jiangsu Teeyer Intelligent Equipment Corp., Ltd

NO.312 Hehai West Road, high Technology Development Zone. Changzhou City, Jiangsu Province, China

+86-13861131181(David CHEN)

davidchen@teeyer.com
sales@teeyer.com